Prime Solar, a subsidiary of Prime Infrastructure Capital Incorporation has launched a 64 MW solar power plant in Tanauan, Batangas in the Philippines. The facility began construction in Q2 2023 and is expected to contribute significantly to the country’s transition towards clean energy.

Moreover, the Tanauan facility will be connected to the grid on June 12, 2024, while the Maragondon plant will follow shortly. Prime Infra is working closely with Manila Electric Company (Meralco) to finalise the necessary details for power dispatch.

In addition to this, Prime Infra is already planning expansions, adding 10 to 12 MW to both the Tanauan and Maragondon facilities by the end of 2024. The company will also evaluate opportunities for further solar power projects in the country, underscoring its commitment to renewable energy (RE) development.