The LRT Jakarta Phase 1B (Velodrome–Manggarai) has achieved full connection of its elevated track, with the 120-metre girder span above the Ir Wiyoto Wiyono Toll Road now completed. The milestone confirms a continuous elevated rail corridor from Kelapa Gading in North Jakarta to Jalan Pramuka in Central Jakarta.

Track works covering 4.7 km are complete, while architectural and MEP works are ongoing at Pramuka BPKP, Pasar Pramuka, Matraman and Manggarai stations. The IDR4.1 trillion project reached 89.22 per cent completion by end-2025 and is targeted to begin operations by mid-2026.