Construction progress on the Jakarta LRT Phase 1B project has reached 80.57 percent as of mid-November 2025 in Indoensia. Rawamangun Station is the most advanced component at 91.69 percent completion, while viaduct works have reached 95.40 percent.
Phase 1B includes the construction of Rawamangun, Pramuka BPKP, Pasar Pramuka, Matraman, and Manggarai stations, with individual progress standing at 65.29 percent, 45.24 percent, 65.89 percent, and 30.42 percent respectively. The package covers elevated structures, stations, systems installation and interface works connecting the existing Phase 1 alignment.
The Jakarta Provincial Government and PT Jakarta Propertindo (Jakpro) are also reviewing future extensions, including Phase 1C (Manggarai–Dukuh Atas) and Phase 2A (to Jakarta International Stadium). A new northern LRT corridor from Kelapa Gading to Pantai Indah Kapuk (PIK 2) is under study. The full LRT programme aims to improve connectivity between East, Central, and North Jakarta and integrate with major rail hubs including Manggarai, Dukuh Atas and Halim Perdanakusuma.