The Government of Ho Chi Minh City needs to add approximately 6,000 MW of power capacity to meet rising electricity demand from industrial production and high-tech investments, according to calculations by the municipal Department of Industry and Trade. The city currently consumes around 58 billion kWh of electricity annually, with peak demand of approximately 9,471 MW. By 2030, annual consumption is forecast to reach 93.972 billion kWh, with peak demand rising to around 16,103 MW. Growing investment in data centres and semiconductor manufacturing is increasing pressure on the city’s electricity supply and grid infrastructure.

To support demand at Saigon Hi-Tech Park (SHTP), four 110 kV substations with a combined minimum capacity of 504 MVA are planned for the existing 913-ha site between 2025 and 2030. A further 110 kV substation, with a minimum capacity of 189 MVA, is planned for the 194.84-ha expansion area, bringing the minimum additional capacity requirement across both areas to 693 MVA. SHTP currently has 147 dedicated substations with a total installed capacity of 469,535 kVA. The city is also upgrading its electricity network, expanding transmission lines and substations, and accelerating grid automation.

The city plans to establish a national energy centre in the Ba Ria-Vung Tau area to supply energy, including to data centres. Resolution No. 47/2026/NQ-HDND, adopted on September 22, 2026, expands participation in direct power trading through dedicated connection grids to include LNG-fired power generators and electricity consumers in industrial parks, export processing zones, economic zones, industrial clusters and hi-tech parks. In addition, Pacifico Energy Vietnam has received approval to survey two offshore wind power projects. One project, planned in waters off Ho Chi Minh City, is expected to have a capacity of 500 MW and an estimated investment of USD2 billion.